Best Practices: California’s Title 24 and Electric Signs

May 14, 2019

Government-mandated policies such as California’s Building Code, Title 24 have been instrumental in identifying new ways to reduce energy consumption. Title 24 requires that, by 2030, all new nonresidential construction must meet zero net energy requirements, which means a building cannot emit more energy than it produces. Additionally, Title 24 compliance may be required in existing non-residential buildings in the event of certain lighting alterations. According to the California Energy Commission, standards like Title 24 and other energy efficiency efforts have helped keep the state’s per capita electricity use flat over the last 40 years.

A new document published by UL provides audit instructions, responsibilities of the manufacturer, and technical requirements for the certification of electric signs to the California Energy Commission (CEC) 2016 Building Energy Efficiency Standards Title 24, Part 6 of the California Code of Regulation. Here’s a sampling of the requirements.

Responsibilities of the manufacturer

  • UL markings: restrict the use of markings that reference Title 24 to those products that are found by the manufacturer’s own inspection to comply with the requirements in this document. The use of such markings is further limited by the agreements that have been executed by the subscriber and UL.
  • Access to facilities: during hours in which the factory is in operation, permit the field representative access to any portion of the premises where the product or components thereof are being fabricated, processed, finished or stored. The field representative shall be permitted to audit, prior to shipment, any product bearing or intended to bear markings referencing Title 24 as indicated in this document. If product disassembly is required, the manufacturer shall undertake it.
  • Resolution of non-conformances: perform a root cause analysis of nonconforming test results reported by UL in order to determine and implement appropriate corrective actions. Upon request, the manufacturer shall submit the findings of their analysis and action plan for review and/or monitoring by UL.

Manufacturer’s technical representative (MTR) 

Each manufacturer shall designate and maintain at least one representative that meets the criteria of a manufacturer’s technical representative for energy certification of electric signs to Title 24. To qualify, this individual shall successfully complete the UL University Online curriculum for Title 24 Energy Certification.

Compliance to this requirement will be verified by the UL representative by requesting the Certificate of Completion of the required UL University Sign Course for the designee(s).

Compliance assessment process 

The manufacturer is responsible for conducting and documenting the compliance assessment process on a Master Compliance Record (MCR) for all products intended to bear the UL Title 24 mark.

The compliance evaluation is a review of the sign construction in accordance with all applicable requirements and a determination of compliance with those requirements.

1. Required documentation for each sign or sign construction will include the completion of the Master Compliance Record or MCR. A copy of this document is attached as Exhibit A. This form may be completed and stored electronically or in paper form.

2. For multiple signs identical in construction or for a family of similar signs, the documentation needs only to reference a representative sign or signs. Documented records shall be maintained for each product, group, or family of signs that bear the UL Listing Mark.

Responsibilities of the field representative

  • Audits: perform in-factory audits to review samples of signs bearing, or intending to bear, the UL Title 24 energy efficiency mark. Additionally, the field representative is to audit records of past production if production is not available.
  • MTR verification: during each Factory Visit, the UL field representative will verify the manufacturer has a qualified “manufacturer’s technical representative” that meets the requirements specified in the “Responsibilities of the manufacturer” section above. The manufacturer will be issued a document from UL University indicating successful completion of the course. This document is to be kept on file by the manufacturer to facilitate MTR verification by the field representative.
  • Instructions for inspection reports: an inspection report is to be completed for the energy inspection and a copy is to be provided to the sign manufacturer. A separate inspection is to be completed for the energy audit; reports are not to be combined with the safety inspection.
  • Instructions for variation notices (VNs): any nonconformance to the technical or documentation requirements found during the audit is to be documented on a variation notice. Corrective action is to be taken by the manufacturer if a sign displaying, or intended to display, the Title 24 Energy Certification mark does not conform to the requirements contained in this document.

Technical requirements — general

Sign lighting energy standards apply to both indoor and outdoor signs and contain two different prescriptive compliance options:

  • Option A: maximum allowed lighting power (also referred to as the watts per square foot approach)
  • Option B: Specific lighting source approach.

Either approach may be utilized to determine compliance.

Approach 1. maximum allowed lighting power approach (watts per square foot approach)

Maximum allowed lighting power approach specifies a maximum lighting power that can be installed, expressed in W/ft2 of sign area. Signs cannot exceed the following power limits:

  • Internally Illuminated – shall not exceed 12 W/ft2
  • Externally Illuminated – shall not exceed 2.3 W/ft2

Steps to determining compliance using the maximum allowed lighting power approach 

1. Determine if the is sign internally or externally illuminated.

2. Calculate area of the sign face.

  • For double-face signs, only one side is used for the calculation
  • For changing message boards use the area of the message board face

3. Determine the total input wattage of the sign.

  • For neon, fluorescent, HID and LED signs use the input amperage (A) multiplied by the input volts (V) of all ballasts or transformers; or the marked input wattage rating (if available).
  • For incandescent signs use the wattage specified on the sign re-lamping label.
  • For changing message boards use the input volts x amps and the area of the board face.

4. Divide the input watts by the calculated sign face area (square ft.).

  • Internally Illuminated – shall not exceed 12 W/ft2
  • Externally Illuminated – shall not exceed 2.3 W/ft2

Approach 2. specific lighting source approach

The specific lighting source approach specifies that signs illuminated exclusively with efficient lighting sources (e.g. electronic ballasts, high efficiency lamps, efficient power supplies and efficient transformers) comply with the energy requirements, regardless of the power consumed.

  • Internally Illuminated – shall not exceed 12 W/ft2
  • Externally Illuminated – Shall not exceed 2.3 W/ft2

The document also identifies light sources to be used with the specific lighting source approach and ;provided a sample master compliance record

See the full document here: industries.ul.com/wp-content/uploads/sites/2/2015/03/Title-24-Brochure.pdf.

Find out more about Title 24: www.energy.ca.gov/title24/

Photo source: Luca Bravo on Unsplash

Related Articles


Changing Scene

  • March 18, 2026 - Liteline Presents ATTRACKT - New Product Webinar - March 31, 2026

    Liteline Presents: ATTRACKT – New Product Webinar – March 31, 2026

    Join Liteline for the launch of ATTRAKT, a low-voltage magnetic lighting system designed for modern spaces. ATTRACKT’s compact, refined form factor delivers exceptional flexibility, with fixtures that can be easily positioned and reconfigured to suit evolving lighting needs. With versatile modules and connectors to create customized layouts, ATTRACKT provides a clean, modular solution that elevates… Read More…

  • March 3, 2026 - Leviton - Certolux Visioneering (Viscor) Announces Walter Lai as New Purchasing Manager

    Leviton – Certolux Visioneering (Viscor) Announces Walter Lai as New Purchasing Manager

    Leviton – Certolux Visioneering (Viscor) is excited to welcome Walter Lai CSCMP to the team as Purchasing Manager! Walter brings over 20 years of expertise in purchasing, inventory management, and supply chain operations. His strong background in supplier management, cost optimization, and leading cross-functional teams will be a tremendous asset as they continue to strengthen… Read More…


Design

  • Prolux Lighting & Controls: Lighting Project Highlight – The Westin Pool, Calgary

    Prolux Lighting & Controls: Lighting Project Highlight – The Westin Pool, Calgary

    Lighting natatorium environments requires fixtures that can withstand humidity, chemicals, and demanding conditions, without compromising the architectural design of the space. For this project, the team specified the LumenWerx VIA2 Seal above the pool with a natatorium finish, designed specifically for high-moisture environments. Traditional natatorium fixtures are often large and bulky to ensure durability, but… Read More…

  • CSC LED: Why Blue Light at Night Is a Problem & How Amber Optics Solve It

    CSC LED: Why Blue Light at Night Is a Problem & How Amber Optics Solve It

    Outdoor lighting plays a critical role in safety, visibility, and security—but not all light is created equal. In recent years, increased awareness around blue-rich white light has raised important questions about its impact on human health, wildlife, and the night sky. As municipalities, designers, and property owners look for better solutions, Amber Optics are becoming… Read More…


New Products

  • Magic Lite: Modern Pathway Light

    Magic Lite: Modern Pathway Light

    Discover the subtle elegance of the L-shaped Modern Pathway Light from Magic Lite, designed to complement contemporary outdoor settings with its sleek and classy design. This pathway light is perfect for those looking to enhance their landscape with a reliable, energy-efficient lighting solution. Read More…

  • LEDVANCE: Jelly Jar Light, Hazardous Location – HAZ JJAR 020 UNH D 8 30 CSL GR

    LEDVANCE: Jelly Jar Light, Hazardous Location – HAZ JJAR 020 UNH D 8 30 CSL GR

    Designed for durability and safety in demanding environments, the LEDVANCE Jelly Jar Hazardous Location light features a compact structure with a robust metal guard. It supports multiple installation options to suit a variety of industrial and hazardous location applications and is an ideal choice for areas requiring reliable, rugged illumination. Read More…